  • Project Commencement
    • November 2009
  • Requirements Gathering ERP System
    • Plan – December 2009 through February 2010
    • Design – February 2010 through April 2010
  • Upgrade Existing System – Financials
    • Design – December 2009 through May 2010
  • Fit/Gap Analysis
    • Design – March 2010 through July 2010
  • TxDOT and DIR Financials
    • Design – December 2009 through January 2011
    • Build – August 2010 through February 2011
    • Deliver – June 2011 through August 2011
    • Operate – September 2011 through October 2011
  • HR/Payroll
    • Summer 2012