- Project Commencement
- Requirements Gathering ERP System
- Plan – December 2009 through February 2010
- Design – February 2010 through April 2010
- Upgrade Existing System – Financials
- Design – December 2009 through May 2010
- Fit/Gap Analysis
- Design – March 2010 through July 2010
- TxDOT and DIR Financials
- Design – December 2009 through January 2011
- Build – August 2010 through February 2011
- Deliver – June 2011 through August 2011
- Operate – September 2011 through October 2011
- HR/Payroll